Connection to the power grid: you will mount solar panels with an installed capacity of ≤10.8 kW on an existing house and want prosumer certification before connection (the installed capacity is at most equal to the absorbed power).

Connection to the power grid stages and steps
See the stages and the steps you need to follow if you want to mount photovoltaic panels with an installed capacity of ≤10.8 kW (at most equal to the absorbed power) on an existing house and obtain prosumer certification before completing the connection installation.
Submitting the connection to the power grid documentation
Responsible:
prosumerEstimated duration:
1 calendar dayDownload the connection to the power grid notification (Appendix 5) here, complete it, and submit it to us from your online account.
In addition to the connection to the power grid notification, we expect other documents from you, which are mentioned in the notification.
Application review and documentation verification
Responsible:
distributorRegulated duration:
7 working daysWe will review your application and the submitted documents and provide a response within a maximum of seven working days. In our response, which will be sent to your online account, we will indicate any additional documents specific to your generation installation that need to be submitted.
Updating the connection to the power grid certificate
Responsible:
distributorRegulated duration:
14 working daysAfter installing the generation system and submitting its documentation to us, we will update the connection certificate within a maximum of 14 days from the submission date. The connection to the power grid certificate confirms the presence of a new consumption and generation point in the network. Within the same 14-day period, we will also replace the electricity meter.
Signing the purchase-sale contract
Responsible:
prosumerEstimated duration:
1 calendar dayYou will sign a purchase-sale contract for the electricity you generate and inject into the distribution network with a supplier.