Responsible:

prosumer

Estimated duration:

1 calendar day

Download the connection to the power grid notification (Appendix 5) here, complete it, and submit it to us from your online account.

Create an online account

In addition to the connection to the power grid notification, we expect other documents from you, which are mentioned in the notification.

Responsible:

distributor

Regulated duration:

7 working days

We will review your application and the submitted documents and provide a response within a maximum of seven working days. In our response, which will be sent to your online account, we will indicate any additional documents specific to your generation installation that need to be submitted.

Responsible:

distributor

Regulated duration:

14 working days

After installing the generation system and submitting its documentation to us, we will update the connection certificate within a maximum of 14 days from the submission date. The connection to the power grid certificate confirms the presence of a new consumption and generation point in the network. Within the same 14-day period, we will also replace the electricity meter.

Responsible:

prosumer

Estimated duration:

1 calendar day

You will sign a purchase-sale contract for the electricity you generate and inject into the distribution network with a supplier.