Power supplementation with connection to the power grid installation modification

Stages
Before requesting a power supplementation, we recommend checking the approved power (maximum simultaneous power that can be absorbed) at your desired consumption place, as stated in the ATR or the connection certificate. Then, calculate the total power of all the consumers you want to use at the same time. To find out the total power, use the table “Guide for completing the ATR request and questionnaire (for consumers)”, on the page “Requests and documents“.
Submitting the power supplementation request and necessary documentation
Responsible:
clientEstimated duration:
1 calendar dayThe first step in obtaining the power supplementation is to submit a request – either through your online account or physically at one of your electricity supplier’s offices.
You can find power supplementation requests here under the name “connection requests.” Make sure to check the “dezvoltarea unui utilizator existent” box when filling in the connection request. In addition to the power supplementation request, you must also submit other documents at this stage, which you can learn more about here.
Evaluating the request and verifying documentation
Responsible:
distributorRegulated duration:
10 working daysWe evaluate the request and submitted documentation and respond within a maximum of ten working days – either in your account (if you submitted the documents online) or through your supplier.
You will also receive the invoice for issuing the ATR. We will send the ATR after you pay this invoice. Information about the costs of issuing the ATR and connection can be found here. Follow the payment instructions on the invoice.
Establishing the connection solution and issuing the ATR
Responsible:
distributorRegulated duration:
30 calendar daysWe, the distribution operator, establish the technical connection to the power grid solution (installation route and required materials) within a maximum of 30 working days and, based on this, determine the connection costs. These details will be included in the ATR, which we issue, but you will receive it only after paying the invoice from the previous step.
Once you obtain the ATR, you can contest it if, for example, the proposed connection solution does not seem suitable. You can do this by submitting a request online through your account or physically through the supplier within a maximum of 30 calendar days from receiving the ATR. You will receive our response within a maximum of 30 calendar days.
Submitting the request for signing the connection to the power grid contract
Responsible:
clientEstimated duration:
1 calendar dayFor the actual connection works to begin, you need to decide whether you will perform them with us, the distribution operator, or through a company certified by the National Energy Regulatory Authority (ANRE). The list of ANRE-certified companies can be found here.
Then, you will need to pay the invoice for issuing the ATR if you have not done so already. Once you have the ATR, download the request for signing the connection and design/execution contract from here. Complete it and send it to us either through your online account or through your supplier.
Evaluating the request and sending the proposed connection to the power grid contract
Responsible:
distributorRegulated duration:
5 working daysWe will evaluate your request and return with the proposed connection to the power grid contract within a maximum of five working days.
Signing the connection to the power grid contract
Responsible:
clientEstimated duration:
1 calendar dayYou sign the connection contract received from us.
Paying the connection to the power grid fee
Responsible:
clientEstimated duration:
15 calendar daysYou pay the connection the power grid costs, which are included and detailed in the connection contract.
Design and execution of the connection to the power grid
Responsible:
distributor or a firmEstimated duration:
90 calendar daysThe distributor or the ANRE-certified company you selected will design and execute the connection works. At this stage, additional documents or permits for the works may be required, which will be obtained by the project executor. These documents/permits will reach us either through your online account or through your supplier. Once all permits are obtained, execution works will begin, which must be completed within a maximum of 90 calendar days. Create an online account.
Submitting the usage installation file
Responsible:
clientEstimated duration:
1 calendar dayA company certified by ANRE, chosen by you, prepares the usage installation file, which includes several necessary documents for the connection process to continue. You will pay a negotiated amount directly to the chosen company for preparing the file. The complete file must reach us – either through the online account, through your supplier, by email (to the address indicated in the ATR), or directly by uploading it here.
Reception and commissioning of the connection to the power grid installation
Responsible:
distributorRegulated duration:
5 working daysWe verify the executed works, and if everything is in order, we commission the connection to the power grid installation (the installation outside your property up to the meter).
Issuing the connection to the power grid certificate
Responsible:
distributorRegulated duration:
3 working daysWithin a maximum of three days after completing the previous step, we issue a new connection to the power grid certificate.
Energizing the user installation and reprogramming the meter
Responsible:
distributorRegulated duration:
5 working daysWe will energize the user installation and reprogram the meter.
Reimbursement of connection design and wiring execution
Responsible:
distributorEstimated duration:
30 calendar daysAt the end of the connection to the power grid process, we will adjust the costs based on the expenses stated in the ATR and other documents submitted by the project executor. After cost adjustment, if applicable, we will reimburse you (directly or through the executor) part of the expenses incurred for the connection, based on a calculation formula established by ANRE.