Connection to the power grid: building a house and installing panels with installed capacity below 400 kW

Steps for connecting to the power grid
Connecting to the power grid involves several steps, which we have splited below into stages and steps to make the process easier to follow.
Submitting the connection to the power grid request and required documentation
Responsible:
prosumerEstimated duration:
1 dayThe power grid connection process starts when you submit a connection request (Appendix 1) to us, the distribution operator.
After completing it, it is important to send it to us. Create an online account on our website and upload the completed request.
Evaluation of the request and verification of documentation
Responsible:
distributorRegulated duration:
5 working daysIf the documents are complete and correct, you will receive the invoice for the technical grid connection approval (ATR). After paying the invoice, you will receive the ATR. Information about the costs related to issuing the ATR and the connection to the power grid can be found here.
Payment instructions are included in the issued invoice. If the documents are incomplete or incorrect, you will receive a response with the necessary clarifications or modifications.
Determining the connection to the power grid solution and issuing the ATR
Responsible:
distributorRegulated duration:
15 working daysThe distribution operator determines the technical connection solution (the route and necessary materials) within a maximum of 15 working days. These details will be included in the ATR, which you will receive after paying the invoice. If you are not satisfied with the proposed technical solution, you can contest the ATR within 30 calendar days. We will respond within a maximum of 30 calendar days.
Submitting the request for signing the connection to the power grid contract
Responsible:
prosumerEstimated duration:
1 calendar dayTo start the power grid connection works, you need to choose whether they will be carried out by the distribution operator or by a company certified by the National Energy Regulatory Authority (ANRE).
After choosing the option, make sure you have paid the ATR invoice if you haven’t already. Once you have obtained the ATR, download the request for signing the connection contract from here, complete it, and send it to us from your online account.
Evaluation of the request and transmission of the proposed connection to the power grid contract
Responsible:
distributorRegulated duration:
3 working daysAfter evaluating the request, if all information is correct and complete, we will send you the connection to the power grid contract within a maximum of three working days.
Signing the connection to the power grid contract
Responsible:
prosumerEstimated duration:
1 calendar dayYou sign the connection to the power grid contract you received from us.
Paying the connection to the power grid fee
Responsible:
prosumerEstimated duration:
15 calendar daysYou pay the connection to the power grid costs according to the details in the connection contract.
Design and execution of the connection to the power grid installation
Responsible:
distributor or firmEstimated duration:
90 calendar daysThe distribution operator or the company certified by ANRE will design and execute the connection to the power grid works. In this step, certain additional documents or approvals may be required, which the executor will obtain. The documents will be transmitted online. After obtaining all approvals, the execution works for your connection must be completed within a maximum of 90 calendar days.
Submitting the usage installation file
Responsible:
prosumerEstimated duration:
1 calendar dayA company certified by ANRE, chosen by you, prepares the usage installation file, which contains the necessary documents to continue the process. Additional information about the usage file can be found here. The complete file can be sent from the online account, via email, or uploaded directly here.
Reception and commissioning of the grid connection installation
Responsible:
distributorRegulated duration:
5 working daysWe verify the executed works, and if everything is in order, the grid connection installation (the installation outside your property, up to the meter) will be put into operation.
Issuing the grid connection certificate
Responsible:
distributorRegulated duration:
3 working daysWithin three days after completing the works and conducting the tests, we issue the grid connection certificate, a document confirming that your new consumption and production location is connected to the grid.
Signing the supply contract
Responsible:
prosumerEstimated duration:
1 calendar dayTo use and inject electricity into the power grid, you must sign a contract with an electricity supplier. After signing the contract, we will install the meter at your home.
Commissioning the usage installation and installing the meter
Responsible:
distributorRegulated duration:
5 working daysAfter signing the contract with the supplier, we will install the electric meter and energize the usage installation within a maximum of five working days.
Reimbursement of costs for the design and wiring execution
Responsible:
distributorEstimated duration:
30 calendar daysAt the end of the grid connection process, we will recalculate the costs based on the documents and expenses provided in the ATR. If applicable, you will receive a partial reimbursement of costs, according to the calculation formulas established by ANRE that we apply.
You might also be interested in:

Terms for everyone to understand

Requests and useful documents for connection to the power grid
