Compensations you may receive for connection to the power grid delays
Connecting to the power grid is very important, whether you are undergoing this process for a house under construction or for an increase in power supply.

The most important role in connection to grid is ours, as the distribution operator. That’s why we try to complete the stages we are responsible for as quickly as possible. Moreover, we are legally required to meet certain deadlines. If we fail to do so, you are entitled to receive compensations from us, as stipulated by law in the Performance Standard for the distribution service.
See below what compensations you may receive if we delay certain steps in the process of connecting to the power grid:
Voltage level | Situation | Maximum response time | Compensation for individuals | Compensation for businesses |
---|---|---|---|---|
Low Voltage (LV) or Medium Voltage (MV) | Time for issuing the connection technical grid connection approval (ATR) based on a solution study | 10 calendar days | 40 RON | 90 RON |
High Voltage (HV) | Time for issuing the ATR based on a solution study | 10 calendar days | 130 RON | 130 RON |
LV or MV | Time for issuing the ATR based on a solution sheet | 30 calendar days | 40 RON | 90 RON |
HV | Time for issuing the ATR based on a solution sheet | 30 calendar days | 130 RON | 130 RON |
LV or MV | Time for issuing the ATR for prosumers with an installed capacity of up to 400 kW | 15 business days | 40 RON | 90 RON |
HV | Time for issuing the ATR for prosumers with an installed capacity of up to 400 kW | 15 business days | 130 RON | 130 RON |
LV or MV | Time for issuing the connection certificate (CER) for prosumers with an installed capacity of up to 400 kW | 3 business days | 90 RON | 90 RON |
HV | Time for issuing the CER for prosumers with an installed capacity of up to 400 kW | 3 business days | 130 RON | 130 RON |
LV or MV | Time for sending the connection contract, except for prosumers with an installed capacity of up to 400 kW | 5 business days | 40 RON | 90 RON |
HV | Time for sending the connection contract, except for prosumers with an installed capacity of up to 400 kW | 5 business days | 130 RON | 130 RON |
LV or MV | Time for sending the connection contract, for prosumers with an installed capacity of up to 400 kW | 3 business days | 40 RON | 90 RON |
HV | Time for sending the connection contract, for prosumers with an installed capacity of up to 400 kW | 3 business days | 130 RON | 130 RON |
LV, MV or HV | Time for designing, executing, and commissioning the connection | 90 calendar days from obtaining the construction permit, for works carried out by the distributor | 100 RON | 100 RON |
LV or MV | Time for energizing the user installation, except for prosumers with an installed capacity of up to 400 kW | 5 business days | 90 RON | 90 RON |
HV | Time for energizing the user installation, except for prosumers with an installed capacity of up to 400 kW | 5 business days | 130 RON | 130 RON |
LV or MV | Time for energizing the user installation, for prosumers with an installed capacity of up to 400 kW | 2 business days | 90 RON | 90 RON |
HV | Time for energizing the user installation, for prosumers with an installed capacity of up to 400 kW | 2 business days | 130 RON | 130 RON |