Compensations you may receive for connection to the power grid delays

Connecting to the power grid is very important, whether you are undergoing this process for a house under construction or for an increase in power supply.
Femeie cu par alb si ochelari lucrand concentrata la laptop intr-un spatiu modern

The most important role in connection to grid is ours, as the distribution operator. That’s why we try to complete the stages we are responsible for as quickly as possible. Moreover, we are legally required to meet certain deadlines. If we fail to do so, you are entitled to receive compensations from us, as stipulated by law in the Performance Standard for the distribution service.

See below what compensations you may receive if we delay certain steps in the process of connecting to the power grid:

Voltage levelSituationMaximum response timeCompensation for individualsCompensation for businesses
Low Voltage (LV) or Medium Voltage (MV)Time for issuing the connection technical grid connection approval (ATR) based on a solution study10 calendar days40 RON90 RON
High Voltage (HV)Time for issuing the ATR based on a solution study10 calendar days130 RON130 RON
LV or MVTime for issuing the ATR based on a solution sheet30 calendar days40 RON90 RON
HVTime for issuing the ATR based on a solution sheet30 calendar days130 RON130 RON
LV or MVTime for issuing the ATR for prosumers with an installed capacity of up to 400 kW15 business days40 RON90 RON
HVTime for issuing the ATR for prosumers with an installed capacity of up to 400 kW15 business days130 RON130 RON
LV or MVTime for issuing the connection certificate (CER) for prosumers with an installed capacity of up to 400 kW3 business days90 RON90 RON
HVTime for issuing the CER for prosumers with an installed capacity of up to 400 kW3 business days130 RON130 RON
LV or MVTime for sending the connection contract, except for prosumers with an installed capacity of up to 400 kW5 business days40 RON90 RON
HVTime for sending the connection contract, except for prosumers with an installed capacity of up to 400 kW5 business days130 RON130 RON
LV or MVTime for sending the connection contract, for prosumers with an installed capacity of up to 400 kW3 business days40 RON90 RON
HVTime for sending the connection contract, for prosumers with an installed capacity of up to 400 kW3 business days130 RON130 RON
LV, MV or HVTime for designing, executing, and commissioning the connection90 calendar days from obtaining the construction permit, for works carried out by the distributor100 RON100 RON
LV or MVTime for energizing the user installation, except for prosumers with an installed capacity of up to 400 kW5 business days90 RON90 RON
HVTime for energizing the user installation, except for prosumers with an installed capacity of up to 400 kW5 business days130 RON130 RON
LV or MVTime for energizing the user installation, for prosumers with an installed capacity of up to 400 kW2 business days90 RON90 RON
HVTime for energizing the user installation, for prosumers with an installed capacity of up to 400 kW2 business days130 RON130 RON